The project will allow the dualization of an existing single carriageway. A 17 kilometers dual carriageway and service road of a total length of 27 kilometers will be constructed.
Description of work:
• Construction of a 90 meters long post-tensioned three-cell box girder flyover bridge
• Construction of two 53 meters long post-tensioned four-cell box girder interchanges bridges
• Construction of four pedestrian underpasses 4 m x 4 m x 45 m
• Road works including road stretching to approximately 1,000 m
• Construction of a road leading to the UAE’s border check post
• Water drainage, asphalt works, signing and marking
• Public utility service and traffic diversion and protection