Upgrading Tripoli’s infrastructure requires the rehabilitation of several existing services and reconstruction. Utility lines excluding drinking water and electrical lines with an approximate length of 17,000 meters.
Description of work:
• Construction of new collectors
• Connection of existing and new collectors to main line
• Rehabilitation of the existing network in damaged or undersized locations
• The separation of the stormwater and wastewater networks
• Construction of surface drainage systems, including inlets, gullies and interceptors
• Rehabilitation of the new Tripoli area including the installation of the necessary equipment for the provision of drinking water
• Installation of MV and LV cables and connection
• Reconstruction of the road structure: asphalt, base course, subgrade, milling and overlaying
• Landscaping plantation, street furniture such as lighting poles, luminaries
• Testing